All Reports

Voith Hydro, Inc. - Contract No. 9000

Report Number
2021-15786

As part of our annual audit plan, we performed an audit of costs billed to the Tennessee Valley Authority (TVA) by Voith Hydro, Inc. (Voith) under Contract No. 9000, for hydro modernization, unit rehabilitation, and functional support services in support of TVA's hydro facilities, including Raccoon Mountain Pumped Storage Plant. The contract provided for TVA to compensate Voith for these services on either a fixed price, time and material, and/or target price estimate basis.

Audit

Organizational Effectiveness - Allen Integrated Site

Report Number
2022-17335

The Office of the Inspector General conducted a review of the Allen Integrated Site (Allen) to identify factors that could impact Allen’s organizational effectiveness. During the course of our evaluation, we identified positive behavioral factors, including relationships with team members and business units outside Allen; however, we also identified behavioral concerns with two managers. In addition, we identified operational factors needing improvement related to (1) perceptions of ineffective work management, (2) fire alarm system repairs, and (3) site security and access concerns.

Inspection / Evaluation

Independent Examination of Cost Proposal for Coal Combustion Residual Program Management Services

Report Number
2021-17243

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for coal combustion residual (CCR) program management services. Our examination objective was to determine if the company's cost proposal was fairly stated for a planned 20-year contract.In our opinion, the company's proposed markup rates for recovery of indirect costs were fairly stated. However, the company's proposed costs for a $248.2 million CCR project were overstated by a net $1.6 million due to inaccuracies in craft pay and benefits.

Audit

Acquisition and Disposal of Real Property

Report Number
2021-15789

The Office of the Inspector General conducted an evaluation to determine if the Tennessee Valley Authority (TVA) was effectively managing acquisitions and disposals of real property. We determined TVA effectively managed the real property acquisitions and disposals for the sample of transactions we reviewed.

Inspection / Evaluation

Gas and Hydro Human Performance Events

Report Number
2022-17339

Due to an elevated number of human performance events in Gas Operations and Hydro Generation organizations in fiscal year 2020, we initiated an evaluation to determine if TVA was taking appropriate actions in response to human performance events.We determined appropriate actions were taken in response to human performance events in Gas and Hydro. Specifically, we determined (1) actions were taken or planned to be taken in response to human performance events and (2) initiatives were created to improve human performance in the organizations.

Inspection / Evaluation

Jacobs Technology Inc. - Contract No. 11163

Report Number
2021-15787

As part of our annual audit plan, we audited costs billed to the Tennessee Valley Authority (TVA) by Jacobs Technology Inc. (Jacobs) under Contract No. 11163 for construction management services, including design, construction, and project support at various TVA facilities. Our audit objective was to determine if costs were billed in accordance with the contract's terms. Our audit scope included about $21.3 million in costs billed to TVA from July 20, 2017, through April 29, 2020.

Audit

Independent Examination of Cost Proposal for Transmission Construction Services

Report Number
2021-17309

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for transmission construction services. Our examination objective was to determine if the company's cost proposal was fairly stated for a planned 5-year, $25 million contract.In our opinion, the company's cost proposal was overstated. Specifically, the proposed labor markup rates, for recovery of the company's indirect costs, were overstated compared to recent actual costs.

Audit

Independent Examination of Cost Proposal for Transmission Construction Services

Report Number
2021-17307

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for transmission construction services. Our examination objective was to determine if the company's cost proposal was fairly stated for a planned 5-year, $100 million contract.In our opinion, the company's cost proposal was overstated. Specifically, the proposed markup rates on craft wages for recovery of the company's indirect costs were overstated compared to recent actual costs.

Audit

Independent Examination of Cost Proposal for Transmission Construction Services

Report Number
2021-17310

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for transmission construction services. Our examination objective was to determine if the cost proposal was fairly stated for a planned 5-year, $25 million contract.In our opinion, the company's cost proposal was overstated. We found the proposed labor markup rates, for recovery of indirect costs, were overstated compared to recent actual costs.

Audit

Maintenance of TVA-Owned Gas Pipelines

Report Number
2021-15796

The Office of the Inspector General included an audit of the Tennessee Valley Authority’s (TVA) maintenance of its owned gas pipelines in our annual audit plan due to pipeline issues identified at other utilities and potential risks to TVA. Our audit objective was to determine if TVA’s maintenance of its owned gas pipelines is adequate. We found TVA did not provide sufficient oversight of the two Contract Operations Providers and the Contract Engineering Provider.

Audit