Power Operations Arc Flash Protection
Report Information
Recommendations
Execute the plan to update arc flash hazard analyses at plants currently overdue on their review cadence to ensure the analyses are reflective of current plant operating conditions and comply with requirements for a 5-year review.
Implement a consistent method for placing updated arc flash labels at plants to provide workers accurate arc flash values in a timely manner.
Consider implementing processes to maintain plant-level inventory listings of arc flash PPE and implementing a PM program to routinely inspect PPE.
Develop and implement a control to ensure arc flash hazard analyses are accurate, approved, and submitted for record into ECM.
Develop and implement a control to ensure arc flash hazard analyses contain all updated calculations at those respective plants.