Description
We reviewed $5.7 million of payments TVA made to a contractor for providing analysis and licensing support for tritium production at Sequoyah Nuclear Plant and determined the contractor had overbilled TVA $78,653. The overbilling included (1) an estimated $76,075 in unsupported labor costs and (2) $2,578 for travel and material costs that were either unsupported or ineligible. TVA management is planning to recover the overbilled costs. Summary Only